A tangle of overhead wires on Glover in Fort Langley. Work on moving the lines underground is scheduled to begin Nov. 7.

Undergrounding lines in Fort Langley set to resume after long shutdown

Letter from Township indicates project will be completed about a year later than planned

Work on eliminating overhead utility poles in downtown Fort Langley is about to resume following a shutdown of several months caused by a demand for design changes by BC Hydro and CN Rail.

A letter to area residents from the Township said construction will resume on Nov. 7.

“Thank you for your patience while construction has been under review and the contractor has been demobilized from the site,” said the message.

The pause of at least three months happened because BC Hydro and CN Rail wanted design changes.

The letter said since late 2016, “discussions have been ongoing between the Township, CN Rail, BC Hydro and benefiting property owners to gain acceptance of the revised civil works.”

In response to a Times query, the Township confirmed that the revisions included allowing above-ground electrical connections to private properties that would have trouble accessing a below-ground line.

CN Rail had concerns about running underground lines beneath its tracks and wanted seismic upgrades to the retaining wall at the heritage railway station.

The postponement is part of the reason why the sidewalk around the new Coulter Berry building on Glover has been left unfinished.

Completion of the building was held up because of a court battle involving the Township and opponents of the project.

That meant installing the underground conduits under the sidewalk was also delayed and before it could be carried out, everything was put on hold while talks with CN Rail and BC Hydro were underway.

The Township letter said all the remaining work, including the Coulter Berry conduits, will be completed over the next 11 weeks, weather permitting.

Once that is done, and CN Rail and BC Hydro have signed off, Hydro, Telus and the other utility companies will be able to start running lines through the underground conduits.

Following that, connections will be switched to the underground system and the utility poles and overhead wires will be removed along Glover from south of 96 Avenue to the Jacob Haldi Bridge, and on Mavis Avenue from McBride Street to River Road.

“The estimated schedule to complete the project is mid-to-late 2017,” the letter reads.

That is about a year behind schedule.

When the ground-breaking ceremony for the undergrounding project was staged in May 2015, the projected completion date was to be August of this year.

The $3 million project was approved by council in 2012 following a 51.5 per cent vote in favour by property owners representing 53.4 per cent of the assessed property values within the Local Area Service (LAS) region covered by the petition.

At the time, some Fort Langley property owners complained they were being unfairly forced to pay for the undergrounding because the system allows someone who owns multiple taxable properties to vote multiple times.

One opponent sent a email to the mayor and council calling the overhead lines “heritage telephone poles” that should be preserved as “a special reminder of the past.”


Just Posted

Top 10 Langley City attractions listed

Discover Langley City unveils first City-centric promotional pamphlet

Langley man wins dismissal of charge for failing to remain at accident scene

Driver said he didn’t realize he’d hit 62-year-old man

Meeting at Langley Seniors Centre about embracing technology

Langley Seniors Community Action Table welcomes speaker March 21

Fraser Valley real estate predicted to slow down in 2018

B.C. Real Estate Association forecasts a cooling market

Vancouver Giants honour their own

Team Awards handed out prior to Friday’s game versus Kelowna

VIDEO: B.C. Mounties reunite veteran with lost military medals

RCMP say Zora Singh Tatla, who served in the army in India for 28 years, is the righful owner

Federal government seeks public feedback on pedestrian safety

What safety measures do you think need to improved for pedestrians and cyclists?

Experts urging caution as rabbits die by the hundreds in B.C. city

Province of B.C. confirms more positive tests for rabbit haemorrhagic disease

Canucks snap scoreless streak but fall short in 5-3 loss to Sharks

Swiss forward Timo Meier nets two, including the game-winner, to lead San Jose

4 facts to ring in St. Patrick’s Day

What do you really know about the Irish celebration?

Search continues for 10-year-old Montreal boy missing since Monday

Montreal police said they are exploring every possibility in search for Ariel Jeffrey Kouakou

Airline passenger-rights bill claws back protections for travellers: Advocate

Bill C-49 would double tarmac delays, scrap compensation for flights affected by mechanical failures

Canadian research vessel to explore 19th Century shipwrecks

Commissioned this week in Victoria, the RV David Thompson is Parks Canada’s newest vessel

UPDATED: ‘New wave’ of anti-pipeline protests return to Trans Mountain facility

About 100 demonstrators with Protect the Inlet marched to the Burnaby terminal Saturday

Most Read